THE TOWN OF CENTREVILLE 101 LAWYERS ROW CENTREVILLE, MD 21617

410-758-1180 FAX 410-758-4741 WWW.TOWNOFCENTREVILLE.ORG

MEMORANDUM

September 19, 2024 TO: Carolyn Brinkley, Town Manager FROM: Karen Luffman, Director of Finance RE: EOY Budget Update As of June 30th, the Town completed the end-year mark of Fiscal Year (FY) 2024. At this time, departments should be at or around 100% of budget spent. The following is information to further explain certain line items:

GF Revenue – 109% received ($557,404 above estimated budget) – The differences are in Local income tax and Public Utility Tax.

A10 – 94% spent A70 – 104% spent ($3,665 overspent) –There was an increase in MDIA fees.

A81 – 109% spent ($4,863 overspent) – Unexpected purchase of HVAC for unit in 105N Liberty.

A92 – 88% spent B10 – 84% spent B22 – 100% spent C11 – 88% spent C22 – 98% spent D10 – 104% spent H40 – 167% spent ($26,794 overspent) 212% received ($32,665 extra received) – The overage in expenses is based on a Main Street Improvement Grant not budgeted for.

H60 – 99% spent H90 – 96% spent EF Revenue – 103% received ($93,766 above estimated budget) – The differences are in investment earnings and water revenue.

7-C21 – 102% spent ($19,200 overspent) -The overage in this was based on electricity charges increasing after budget.

7-C24 – 104% spent ($39,461 overspent) – Shipment of 200 water meters came in 9 months earlier than anticipated. 120 Water invoices are included in this department and are covered by a grant. Meter Installation contracted to VEPO to install meters in large quantities.

7-C25 – 132% spent ($18,969 overspent) – Aging infrastructure and repairs that needed to be fixed.

Total General Fund Budget Amendment - $35,322 Total Enterprise Fund Budget Amendment - $77,630

An unhandled error has occurred. Reload 🗙

Rejoining the server...

Rejoin failed... trying again in seconds.

Failed to rejoin.
Please retry or reload the page.

The session has been paused by the server.

Failed to resume the session.
Please retry or reload the page.